Industrial Warehouse Units Phase II
Cinnamon Brow Business Park, Wigan
Construction Photos
March 2008 Site Levelled and prepared for construction ...
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
April 2008 Foundations for building A and drainage started ...
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
10th April 2008 Steel erected for Building A ...
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
1st May 2008 Brick work & cladding started Building A ...
![]() |
![]() |
![]() |
10th May 2008 Slab work starts Building A ...
![]() |
![]() |
![]() |
11th May 2008 steel work starts Building B ...
![]() |
![]() |
![]() |
19th May 2008 Building A Floor slab complete and cladding started ...
![]() |
![]() |
![]() |
27th May 2008 Building B Steel work complete ...
![]() |
![]() |
![]() |
20th June 2008 Building B roof and Brick work under construction ...
![]() |
![]() |
![]() |
2nd July 2008 Building B pre slab floor preparation ...
![]() |
![]() |
![]() |
2nd July 2008 Building B cladding started ...
![]() |
![]() |
![]() |
28th August 2008 Preparing Yard area for concreting ...
![]() |
![]() |
![]() |